First check the SMTP server is installed in the server. You can check that on Server Manger and Features section.

image_thumb9_thumb

If it is not installed first you need to install the SMTP in the server. SMTP server needs port 25 opens in the firewall in default.

After setting up the SMTP server you need to open the IIS Manger.

image_thumb12_thumb

before stating the SMTP Virtual server need to configure some properties. Right click the SMTP virtual Server and click on the Access Tab. Click on Relay.. button on the Relay restrictions.

image_thumb15_thumb

This section specified which server can use the SMTP for mail relay. So either you need to select Only the list below and add IP Addresses of all server which used to send the emails (ex:-WFE, APP) or let all servers to send emails by All except the list below and putting nothing on the list.

image_thumb19_thumb

Then Click on Authentication.. button on Access Control section and make the checkbox for Anonymous access.

image_thumb22_thumb

Then click ok and go to the Delivery Tab.

image_thumb[2]

Outbound Security section allows you to provide credential for receiving server. Since we are using local SMTP server you can make this as a Basic authentication and type your User name and Password and click the TLS encryption.

image

Outbound Connection section you can change the default port using.

image

Advanced.. section you need specify the Smart host for forwarding the email for Gmail SMTP server (smtp.gmail.com).

You can route all outgoing messages for remote domains through a smart host instead of sending them directly to the domain. This permits you to route messages over a connection that may be more direct or less costly than other routes. The smart host is similar to the route domain option for remote domains. The difference is that after a smart host is designated, all outgoing messages are routed to that server. With a route domain, only messages for the remote domain are routed to a specific server.

image

You can find the Gmail SMTP server settings here.

Then start the SMTP virtual server.

image_thumb[19]

After that you can find the fully qualified name in General Tab and proceed with the Outbound SMTP settings as Part 1.

image_thumb[16]

Comments

Scott R said…
Greeat blog you have

Popular posts from this blog

How to Link Two List and Create a combine view in the SharePoint 2010

In this way you can join multiple list together and can create a combine view. for an example assume that you are managing a list for some events. And also you are having a participants in separate list. Thus you want to join the two list and create a composite view. SharePoint 2010 allows you to create this kind of view using  Linked Data Source. in this approach you can create your own custom list in the SharePoint. How to Create a Linked Data source Go to SharePoint designer and  go to the link called data sources. And Click the Linked Data Source button in the ribbon. Then SharePoint designer will prompt following kind of a dialog. In there add two list, that you wan to linked together. I'm adding airline schedule and booking list. those are the two list that i wan to merge. then click next. And it will guide you another screen. it will ask you to select either Merge Merge use to combine list which are having same columns definition. for and example we can s...

How to Improve Workflow Performance in SharePoint Server 2010

SharePoint workflows are getting  slow for several reasons. in my environment I'm having a problem with following performance issues, therefore in my environment i got following problems. When a item added to the library it takes some times to initiate the workflow. Workflow mail generating is not very fast sometimes. Workflows takes more time to process “Due to heavy load, the latest workflow operation has been queued. It will attempt to resume at a later time” is coming sometimes. I had a custom workflow approval web part and it is taking more than 30 seconds to proceed. Work Done I had a custom workflow approval web part and it is taking more than 30 seconds to proceed. here in my custom web part there is the function which is programmatically updating the workflow. SPWorkflowTask.AlterTask(item, data, false) the last parameter mentioning whether it is synchronous asynchronous. if  is it true it it will wait until workflow schedule accept the workflow task. ...

How to Customize New Item Form to take parameters from Query String in the SharePoint 2010

In here I'm going to explain how to customize the SharePoint Item From to take parameters from Query String and set them as default values using SharePoint designer. Using this you can open a new Item From by providing parameters as query string. For an example you can customize one item Display form and taking query String Parameter from that and view New Item view for another list by providing default values using the Query String.     Steps Open the SharePoint designer and go to list and libraries and open the list that you want. Click the New and create a New Insert View by providing the name of the view.   Then created one will come to the list. then click and open the view. Then default New Item Screen will be loaded as follows. Then Delete the default list view and make that empty. You can delete the controls by selecting the area in the design view, If it fully cleared you can view the following message from the designer. Then go to SharePoint...